Service Image

Maintenance

  • Bolt check all connections throughout the switchboard to the required torque setting and paint to give a visual indication that the connections have been checked
  • Testing as detailed under our Testing & Commissioning documents
  • Check Incoming & Outgoing devices for correct operation and continuity
  • Inspection of ARC shoots with the Air Circuit Breaker
  • Prove the Trip unit within the ACB functions correctly
  • Check that the changeover system whether Electrical, Mechanical or both functions correctly
  • Check the Metering is set up correctly, and functions correctly
  • Replace / Fit Danger labels and Phase labels where required
  • Clean Switchboard inside and out
  • Thermo graphic surveying
  • Harmonic Analysis and Mains Monitoring
  • We have all the necessary portable equipment for on site maintenance and servicing of devices